In the Task Cost Entry Table, you are asked if you want to ignore the task that MacProject II cannot locate and continue importing data, or cancel the import operation altogether.
Imported data must match the data types of the columns of the active chart. That is, names must be imported to name columns, dates to date columns, and so on. If the columns do not match, MacProject II will give you a warning.
-- part contents for card part 4
----- text -----
3 of 3
-- part contents for background part 31
----- text -----
Importing & Exporting Data
-- part contents for background part 32
----- text -----
Importing Data
-- part contents for background part 7
----- text -----
You can change either the imported data or the chart to make the two match properly, then try importing again.
Fields in the Project Table that are calculated by MacProject II, such as Earliest Finish, Slack, and Resource Duration, are not replaced by imported data. Any data that you attempt to import to these fields will be ignored.